Pressure wash all surface's to receive the Xypex Chemical waterproofing system.
From footings to the 2nd level and all horizontal joints are coated.
After filling all tie holes with Xypex Patch'N Plug apply one coat of Xypex Concentrate at 1.5 lb. per square yard then cure.
Then apply one coat of Xypex Modified at a rate of 1.5 lb. per square yard then cure.
Pressure washing and 2 coat application can be done in the same day.
Back filling may commence within 36 hours.  Please review the Xypex Chemical Corporation Specification + Application manual.
     
 